The Rookie
20th April 2019, 09:31 PM
Hi all!
I was wondering if I could get some feedback on a procedure that I was given. This is to be carried out on a new mold after the barrel and mold temperatures are at operating conditions. I attached the full procedure, but I am just curious as to what most people do for setting up the initial shot size.
The Short Shot Setup
At the end of this procedure, the parts should appear cosmetically perfect. The dimensions of the parts may not be optimum, but they should look complete.
Shot Size Estimations
1. Determine maximum stroke for the machine
2. Set shot size to 80% of this value
3. Turn off melt decompression
4. Determine maximum shot pressure for the machine
5. Set injection pressure to 50% of this value
6. Set pack pressure to 0 psi
7. Set hold time to 0 seconds
8. Set injection speeds to 50% of the machine maximum
9. Ensure machine is transferring on position
10. Set transfer position to 0.01 inches
Transfer Position Estimations
1. After purging procedure, prepare a shot
2. Manually move the unit forward
3. Manually inject the shot into the mold for 1 second
4. Record the cushion
5. With injection unit still forward, prepare next shot
6. Manually retract the injection unit
7. Open the mold and eject the parts
8. Repeat 3 times
9. Calculate average cushion
Transfer Position Adjustments
Part Observation
New Transfer Position
Very Short
Average Cushion - 20% of total shot capacity
Short
Average Cushion - 10% of total shot capacity
Okay
Average Cushion
Flash
Average Cushion + 10% of total shot capacity
Serious Flash
Average Cushion + 20% of total shot capacity
Attempt a Single Cycle
1. Single Cycle Machine
2. Observe Transfer Position
3. If the screw makes transfer, re-cycle and proceed
4. If the screw stalls before making transfer, switch to manual, make a shot, move the unit away, and eject the part. Add 10% of the total shot capacity of the machine to the transfer position and try again
Injection Pressure Setting
1. Adjust transfer position to achieve an 80% filled part
2. Set injection pressure to 30% of the machine maximum
3. Increase the injection pressure in increments of 5% of the machine maximum until the fill time does not increase
Re-couple the Cycle
1. Adjust transfer position to achieve 95-98% filled part
2. Set pack and hold pressure to 50% injection pressure
**Proceed to Viscosity, Cavity Balance, and Gate Seal Studies**
I was wondering if I could get some feedback on a procedure that I was given. This is to be carried out on a new mold after the barrel and mold temperatures are at operating conditions. I attached the full procedure, but I am just curious as to what most people do for setting up the initial shot size.
The Short Shot Setup
At the end of this procedure, the parts should appear cosmetically perfect. The dimensions of the parts may not be optimum, but they should look complete.
Shot Size Estimations
1. Determine maximum stroke for the machine
2. Set shot size to 80% of this value
3. Turn off melt decompression
4. Determine maximum shot pressure for the machine
5. Set injection pressure to 50% of this value
6. Set pack pressure to 0 psi
7. Set hold time to 0 seconds
8. Set injection speeds to 50% of the machine maximum
9. Ensure machine is transferring on position
10. Set transfer position to 0.01 inches
Transfer Position Estimations
1. After purging procedure, prepare a shot
2. Manually move the unit forward
3. Manually inject the shot into the mold for 1 second
4. Record the cushion
5. With injection unit still forward, prepare next shot
6. Manually retract the injection unit
7. Open the mold and eject the parts
8. Repeat 3 times
9. Calculate average cushion
Transfer Position Adjustments
Part Observation
New Transfer Position
Very Short
Average Cushion - 20% of total shot capacity
Short
Average Cushion - 10% of total shot capacity
Okay
Average Cushion
Flash
Average Cushion + 10% of total shot capacity
Serious Flash
Average Cushion + 20% of total shot capacity
Attempt a Single Cycle
1. Single Cycle Machine
2. Observe Transfer Position
3. If the screw makes transfer, re-cycle and proceed
4. If the screw stalls before making transfer, switch to manual, make a shot, move the unit away, and eject the part. Add 10% of the total shot capacity of the machine to the transfer position and try again
Injection Pressure Setting
1. Adjust transfer position to achieve an 80% filled part
2. Set injection pressure to 30% of the machine maximum
3. Increase the injection pressure in increments of 5% of the machine maximum until the fill time does not increase
Re-couple the Cycle
1. Adjust transfer position to achieve 95-98% filled part
2. Set pack and hold pressure to 50% injection pressure
**Proceed to Viscosity, Cavity Balance, and Gate Seal Studies**